US data centers are building their own gas plants to skip the grid connection queue

US data centers are building their own gas plants to skip the grid connection queue
Image: Vanessa Guerra
Article · Martech
Reading
6 min
Tables
1
In short

More than 100 gas plants

The bottleneck that became a business model

Connecting a data center to the power grid in the United States can take up to a decade. That's how long grid operators spend studying transmission and transformer upgrades before clearing the connection, and the developer usually ends up splitting the bill for that work. For those racing to bring AI capacity online, that wait has become the industry's most expensive bottleneck.

A large part of the market's response, according to reporting by MIT Technology Review, has been to skip the line: building their own power plant, connected directly to the data center building, without relying on the local utility. This is the so-called "behind the meter" model, in which the generation plant sits on the customer's side, not the public grid's side.

The biggest motivator for on-site power right now from data centers is speed.

Musfika Mishi, associate at BloombergNEF

The numbers behind the race

By October 2026, data center developers had already announced plans for more than 100 behind-the-meter gas plants in the United States, according to data from market intelligence firm Cleanview. Combined capacity exceeds 115 gigawatts, more than double the entire state of California's peak power demand. The vast majority of those announcements came from early 2025 onward, which shows how recently the movement has accelerated.

SourceMetricValue
CleanviewAnnounced plants (US)more than 100 projects
CleanviewPlanned capacitymore than 115 GW
CleanviewOperating today4.9 GW
CleanviewUnder construction15.8 GW
BloombergNEFGlobal announced capacity181 GW (90% in the US)

The gap between what's been announced and what's actually up and running is huge: only a small fraction of the projects are built or operating. But the direction of the movement is already clear enough to worry regulators and energy consultancies.

The xAI case in Memphis

The most cited example of the phenomenon is xAI's campus in Memphis, which since 2024 has operated dozens of natural gas turbines, some of them without environmental permits. At the time, it was a rarity that drew heavy regulatory scrutiny, and the case remains in litigation to this day. What was an exception in 2024 became a strategy replicated by dozens of other projects in under two years.

"This shift in data center developers' energy strategy, toward off-grid gas, raises important questions about how data centers will be powered going forward," says Brendan Pierpont, electricity director at the think tank Energy Innovation, in a statement to MIT Technology Review. In his view, in many cases the on-site plant is just a bridge: "It's basically a very expensive way to cover that five-to-seven-year window until these data centers can get a grid connection."

The price of speed: emissions and electricity bills

The problem is that an expensive bridge tends to become permanent infrastructure. After investing heavily in an on-site plant, the operator has an incentive to keep it running even after securing a grid connection, according to Mishi, of BloombergNEF: the risk of fossil fuel "lock-in" is real.

Climate impact also factors into the equation. Today the US power mix still depends on fossil fuels, but nuclear and renewables already account for about 40% of generation, which makes grid connection, on average, a lower-emission option than relying solely on on-site gas. According to BloombergNEF, if every announced behind-the-meter gas project in the US gets built, they could emit 345 million metric tons of CO2 equivalent per year by 2035, 152 million tons more than if those same data centers drew power from the grid. That's a bigger difference than the entire annual emissions of the Netherlands.

There's also an effect on prices. Higher demand for natural gas tends to push the fuel's price up, which could raise bills for roughly 60% of American households that use gas for heating and cooking, according to Matthias Fripp, director of global policy research at Energy Innovation. The effect could even spill over into electricity prices for those who remain connected to the regular grid.

These data centers want a lot of power, and they want it fast, and the grid is not well equipped to provide that. There are potentially good solutions and bad solutions (...) Rushing off the grid and putting in your own behind-the-meter gas is probably a bad way, because it's still going to raise other people's bills, and it's not great for the environment.

Matthias Fripp, director of global policy research at Energy Innovation

What changes for infrastructure decision-makers in Brazil

Brazil doesn't have the same electrical bottleneck as the United States, and its power mix is mostly renewable, but the underlying logic applies just as much to anyone deciding where to host AI workloads here. The fight for data center megawatts is already part of any energy auction or self-generation negotiation in the country, and ANEEL, Brazil's electricity regulator, also has a review queue for large consumers who want to connect to the grid.

The difference is that, in Brazil, the more likely path isn't for the operator to informally build its own gas-fired power plant, as xAI did in Memphis: it's the regulated self-generation model, a PPA (long-term power purchase agreement) with a wind or solar plant, or a partnership with generators that already have surplus capacity. This is my own reading based on the American case, not a fact reported by the source, but the risk parallel is direct: when energy becomes the scarcest item in the equation, whoever locks in a supply contract before competitors gains launch speed, and whoever doesn't gets stuck in line.

For the founder negotiating GPU capacity with a hyperscaler or closing a colocation deal to train a proprietary model, the question is no longer just "which cloud provider" but now also includes "where does that provider's power come from, and what happens if its source falls behind schedule." A vendor that guarantees compute SLAs without guaranteeing the origin and timeline of its energy is passing along a risk that, in the United States, is already showing up as environmental litigation and lawsuits.

The question the board needs to ask

The American case shows a replicable pattern: when demand for AI infrastructure grows faster than regulators' capacity to connect new consumers, part of the market works around the regulation instead of waiting for it. This creates value for whoever executes fast and a liability of regulatory, environmental and public-relations risk for whoever signs the contract.

Before approving a budget for AI capacity expansion, whether in public cloud or dedicated colocation, it's worth asking the CTO three concrete things: what is the contractual origin of the energy powering that environment, what is the guaranteed horizon of that contract, and what changes in cost and SLA if that power source needs to be replaced midway through. In the United States, the answer for a good share of AI data centers today is a private gas plant, hastily built, off the grid and off the regulatory radar, until the courts or the energy market say otherwise.